File photo: Renee Amilcar, general manager of Transit Services at OC Transpo. Photo by Tony Caldwell /POSTMEDIAArticle content
Six years after Ottawa’s LRT Line 1 began operating with 13 stations running along 12.5 km of track through central Ottawa, a completion date for its eastern extension is coming into focus.
THIS CONTENT IS RESERVED FOR SUBSCRIBERS ONLY
Subscribe now to read the latest news in your city and across Canada.
Exclusive articles from Elizabeth Payne, David Pugliese, Andrew Duffy, Bruce Deachman and others. Plus, food reviews and event listings in the weekly newsletter, Ottawa, Out of Office.Unlimited online access to Ottawa Citizen and 15 news sites with one account.Ottawa Citizen ePaper, an electronic replica of the print edition to view on any device, share and comment on.Daily puzzles, including the New York Times Crossword.Support local journalism.SUBSCRIBE TO UNLOCK MORE ARTICLES
Subscribe now to read the latest news in your city and across Canada.
Exclusive articles from Elizabeth Payne, David Pugliese, Andrew Duffy, Bruce Deachman and others. Plus, food reviews and event listings in the weekly newsletter, Ottawa, Out of Office.Unlimited online access to Ottawa Citizen and 15 news sites with one account.Ottawa Citizen ePaper, an electronic replica of the print edition to view on any device, share and comment on.Daily puzzles, including the New York Times Crossword.Support local journalism.REGISTER / SIGN IN TO UNLOCK MORE ARTICLES
Create an account or sign in to continue with your reading experience.
Access articles from across Canada with one account.Share your thoughts and join the conversation in the comments.Enjoy additional articles per month.Get email updates from your favourite authors.THIS ARTICLE IS FREE TO READ REGISTER TO UNLOCK.
Create an account or sign in to continue with your reading experience.
Access articles from across Canada with one accountShare your thoughts and join the conversation in the commentsEnjoy additional articles per monthGet email updates from your favourite authorsSign In or Create an Accountor
Article content
Article content
Extension of the Confederation Line to Trim Road will make it easier for commuters in the city’s expanding east end to travel in and out of the city.
Article content
Final construction activities and train testing are underway and nearing completion on the extension from Blair Road station to Trim Road, according to an update from transit service general manager Renée Amilcar for the city’s March 17 transit committee meeting.
Article content
Article content
The major remaining fleet activities include software upgrades and operator training, said Amilcar.
Article content
By signing up you consent to receive the above newsletter from Postmedia Network Inc.
Article content
The eastern extension is anticipated to open by the end of the year, although no opening date has been set. The initial goal for the extension, which will add five stations, was 2022.
Article content
Communications rooms and device configurations are ongoing at all stations in the east extension and communications testing is expected to be complete by the end of March. In addition, Amilcar said, eight of 22 needed safety certificates for elevators and escalators at the stations have been obtained. Certifications for the remainder are progressing.
Article content
Other ongoing work includes the communication-based train control system. Amilcar said the system is “well advanced with multiple trains continuing to run in loops.” Boundary testing between the existing Stage 1 and Stage 2 territories has been completed.
Article content
Amilcar said correction of trackwork deficiencies is progressing, and finishing work at Montreal, Jeanne d’Arc, Convent Glen, Place d’Orleans and Trim stations is expected to be completed by the end of March.
Article content
Article content
Grading, drainage, guardrail installation and landscaping at the stations is expected to be complete by the end of the second quarter of 2025, the end of June.
Article content
Article content
The final steps before opening include substantial completion, trial running and final safety approval.
Article content
The report offers no exact date for completion but Amilcar said the city will “continue to apply the knowledge gained from previous work, lessons learned and current operations on Line 1,” in addition to recommendations from the public inquiry.
Article content
Completion of the western extension of the Confederation Line will be further down the road. Station construction, roadway work and other work continues, Amilcar said.
Article content
Meanwhile, just over two months since the O-Train Line 2 and Line 4 began running with five-day service, the trains to the city’s south end and the airport began running seven days a week as of Sunday.
Article content
Our website is your destination for up-to-the-minute news, so make sure to bookmark our homepage and sign up for our newsletters so we can keep you informed.
Article content
Article content
GIPHY App Key not set. Please check settings